[单选题]Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
[单选题]Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).
A.fast tracking
A.what-if scenario analysis
B.resource leveling
C.critical chain metho
D.
[单选题]In a project plan,when the project manager scheouies activities,he(or sha)often uses( )method,precedence relationships between acticities are represented by cireles connected by one or more arrows.The length of the arrow represents the duration of the relevant activity.
A.causality diagram
B.Gantt?chart
C.histogram
D.arrow djgram
[单选题]管子表号sch40S中的S表示( )。
A.不锈钢管
B.序列号
C.壁厚代号
[单选题]Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element.
A.relationships
B.resources
C.stakeholders
D.deliverables
[单选题]Project work packages are typically
decomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, and
monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting
[单选题]Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( ) is not a project selection method.
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
[单选题]Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
[单选题]In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.
A.RBS
B.PBS
C.GBS
D.WBS
[单选题]Mr. Smith, who_______ as a teacher in our school for about 20 years, is now our mayor.
A.has worked
B.worke
A.
B.works
C.had worke
D.
[单选题]The earliest method of delivering telecommunications is the( ).
A.telegraph
B.telephone
C.e-mail
D.letter
[单选题]The Thames Tunnel project was more difficult than any previous projects undertaken in Britain.
A.Right
B.Wrong
C.Not mentioned
[单选题]Developing the project schedule is often an
iterative process. It determines the planned start and finish dates for project
activities and milestones. Schedule development can require the review and
revision of duration estimates and resource estimates to create an approved
project schedule that can serve as a baseline to ( ) progress.
A.analyze
A.track
B.level
C.exten
D.
[单选题]The inputs of developing project management plan do not include ().
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes