第3题: [单项选择]某工程项目施工过程中,承包人运料车由于公共道路断路不能向工地运送材料,致使工期拖延5天,承包人就此向发包人提出工期索赔。其理由是发包人应承担外部协调不力责任。此种索赔属于( )。 A. 总索赔 B. 道义索赔 C. 默示索赔 D. 工程变更索赔 参考答案:C 答案解析:[解析] 合同中默示的索赔,即承包人的该项索赔要求,虽然在工程项目的合同条款中没有专门的文字叙述,但可以根据该合同的某些条款的含义,推论出承包人有索赔权。这种经济补偿含义的条款,在合同管理工作中被称为