第30题: [单项选择]All of following should be done by the project manager during project control EXCEPT ______. A. determine that a change has occurred B. ensure that a change is agreed C. make sure all changes are approved by management D. manage changes as they occur 参考答案:C 答案解析:管理层不需要批准所有变更。任命项目经理管理项目就是为了这种原因。 在项目控制过程中,项目经理应该执行的工作不包括——。 A) 确定已经发生变更 B) 确保变更已得到同意<