第12题: [单项选择]A green building is often built on an area of land ______. [A] which has thick forests around [B] which has already been for buildings [C] where people of high income live 参考答案:B 答案解析:细节题。根据第四段最后一句话“Green building are often built on developed land,so that the buildings do not destroy
第20题: [多项选择]《建设工程价款结算暂行办法》规定,工程设计变更涉及合同价款调整的,合同价款调整按下列方法进行() A. 合同中已有适用于变更工程的价格,采用已有的价格变更合同价款 B. 合同中只有类似于变更工程的价格,参照类似价格变更合同价款 C. 合同中没有适用于变更工程的价格,由承包人提出经发包人确认后执行 D. 合同中没有类似于变更工程的价格,由承包人提出经发包人确认后执行 E. 合同中没有类似于变更工程的价格,由发包人确定价格 参考答案:A, B, C, D