第16题: [多项选择]为了清晰、准确地定义工程项目的目标,降低项目实施过程中发生变更的可能性,工程项目目标应满足( )条件。 A. 目标应是具体的,具有可评估性和可量化性,不应含混模糊 B. 目标必须是可以达到的,不能带有任何的风险 C. 在可能的时候,以可交付成果的形式对目标进行说明,如评估报告、设计图纸等 D. 目标应具有时间性,如果目标没有时间限制,可能永远无法达到 E. 目标的可授权性,即每个目标都可授权给具体的人来负责 参考答案:A,C,D,E 答案解析:为了清晰、准确地定义工程项目的目标,降低项目实施过程中发生变更的可能性,工程项目目标应满足如下条件: (1) 目标应是具体的,具有可评估性和可量化性,不应含混模糊; (2) 目标应