第13题: [单项选择]To solve the present social problems the author suggests that we should______. A. return to primitive mode B. take the fundamental realities for granted C. enable man to fully develop his potentialities D. offer higher wages to the workers and employees 参考答案:C 答案解析:最后一段的“man and full development of his potentialities-those of love and of reason-arethe aims of all
第18题: [单项选择]线性工程等节奏流水施工的组织方法具体如下: ①通过分析,找出对工期起主导作用的施工过程②将线性工程对象划分为若干施工过程③根据完成主导施工过程工作的队(组)或机械的每班生产率确定专业队的移动速度④根据这一速度设计其他施工过程的流水作业,使之与主导施工过程相配合其正确的顺序是 ( )。 A. ④②③① B. ②①③④ C. ③①②④ D. ①③②④ 参考答案:B 答案解析:[解析] 由等节奏流水施工的概念及施工组织方法,可以得到正确答案为B。