第21题: [填空题]In the United States the building of landfills is the job of both federal and local governments. 参考答案:N 答案解析:文章第八段第一句话指出“In the United States,taking care of trash and building landfills are local government re
第23题: [多项选择]下列进度控制的措施中,属于组织措施的有( )。 A. 选择承发包模式 B. 进行工程进度的风险分析 C. 落实资金供应的条件 D. 编制项目进度控制的工作流程 E. 进行有关进度控制会议的组织设计 参考答案:D, E 答案解析:本题考查的是进度控制的组织措施的内容。
项目进度控制的组织措施主要有,应编制项目进度控制的工作流程,应进行有关进度控制会议的组织设计。
DE项:DE项属于组织措施,故当选。
AB项:AB项属于管
第29题: [单项选择]Questions 11 to 18 are based on the conversation you have just heard. A. Discussing about their Accountant-general. B. Having an interview. C. Going through a trial in a court. D. Carrying out a program. 参考答案:B 答案解析:[听力原文] W:Thank you so much for applying for the position of the Accountant-general and for coming