第2题:[单选题]The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A.Project scope statement B.Work package C.WBS D.Project scope plan 参考答案:C ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
A.项目范围说明书B.工作包C.WBS?D.项目范围计划