[单选题]( )is a document generated by the creating WBS process that support the WBS, which provides more detailed descriptions of the components in the WBS.
A.The project charter
B.The project scope statement
C.The WBS dictionary
D.The activity list

更多"[单选题]( )is a document generated by "的相关试题:

[单选题]()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.
A.The project?charter
B.The?project?scope statement
C.The?WBS dictionary
D.The?activity list
[单选题]某公司内部使用wb.xyz.com.cn作为访问某服务器的地址,其中wb是_____ 。
A.主机名
B.协议名
C.目录名
D.文件名
[单选题]已知通过一导体环的磁通量在0.04s内由8×10-3Wb均勻地减小到2×10-3Wb。若环的平面法线与磁场方向一致,则环中产生的感应电动势为:
A.0. 05V
B.0. 15V
C.0. 2V
D.0
[单选题]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
A.independent resource
B.individual work load
C.work milestone
D.work package
[单选题]Creating a clear map of where the project is going is an important first step.It lets you identify risks,clarify objectives,and determine if the project even makes sense.The only thing more important than the release plan is not to take it too seriously.Release planning is creating a game plan for your Web project( )what you think you want your Web site to be.The plan is a guide for the content,design elements,and functionality of a Web site to be released to the public,to partners,or internally.It also( )how long the project will take and how much it will cost.What the plan is not is a functional(请作答此空)that defines the project in detail or that produces a budget you can take to the bank.Basically you use a release Plan to do an initial sanity check of the project's( )and worthiness.Release Plans are useful road maps,but don't think of them as guides to the interstate road system.Instead,think of them as the( )used by early explorers-half rumor and guess and half hope and expectation.It's always a good idea to have a map of where a project is headed.
A.specification
B.structure
C.requirement
D.implementation

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码