[单项选择]On offshore drilling units,emergency lighting and each emergency power system must be tested at least once a().
A. day
B. week
C. month
D. year

更多"On offshore drilling units,emergenc"的相关试题:

[单项选择]On offshore drilling units,each EPIRB or SART must be tested once every().
A. day
B. week
C. month
D. year
[单项选择]A mobile offshore drilling unit must display obstruction lights when it is on the waters over the Outer Continental Shelf and is().
A. under tow
B. fixed to the seabed
C. underway
D. All of the above
[单项选择]A report of casualty to a mobile offshore drilling unit must be made in writing to which office? ()
A. Commandant of the Coast Guard
B. Owner of the unit
C. Nearest Coast Guard Marine Safety Office
D. Captain of the nearest port
[单项选择]A mobile offshore drilling unit under tow is approaching a fog bank. When should fog signals be started? ()
A. When the towing vessel enters the fog
B. When the drilling rig enters the fog
C. When the towing vessel can no longer be seen from the rig
D. Immediately
[单项选择]An offshore drilling unit must be equipped with a first aid kit approved by the().
A. Coast Guard
B. American Bureau of Shipping
C. Minerals Management Service
D. Mine Safety and Health Administration
[单项选择]An offshore drilling unit is required to carry on board an operations manual approved by the ().
A. Coast Guard
B. National Cargo Bureau
C. Minerals Management Service
D. builder
[单项选择]A mobile offshore drilling unit will show the day-shape in DIAGRAM 10 to indicate that it is ().
A. at anchor
B. being towed
C. aground
D. drilling
[单项选择]Each emergency generator on a mobile offshore drilling unit,when tested,must be run under a full load for at least().
A. one hour
B. two hours
C. ten hours
D. four hours
[单项选择]The emergency generator or emergency battery is connected to() on most large ships.
A. distribution boards
B. section boards
C. emergency switch boards
D. main switch boards
[单项选择]Temporary Certificates of Inspection for offshore drilling units are effective until the ().
A. Operations Manual is approved
B. Minerals Management Service approval is issued
C. classification society approval is issued
D. permanent Certificate of Inspection is issued
[单项选择]According to the regulations for mobile offshore drilling units,“industrial personnel” are considered to be all persons carried on the ship for the sole purpose of carrying out the industrial business of the unit,except for().
A. the operator's representative
B. the crew required by the Certificate of Inspection
C. the galley personnel
D. the designated person in charge
[单项选择]Each drilling unit equipped with helicopter fuel storage tanks must have the tanks installed as far as practicable from the().
A. landing area and sources of vapor ignition
B. main deck
C. engine room
D. drill floor
[单项选择]The boom stops are installed on an offshore crane to().
A. prevent the boom from being raised too high
B. prevent the boom from swinging
C. support the boom when not in use
D. prevent the boom from being lowered
[单项选择]After reporting a casualty to a mobile offshore drilling unit,which record must be retained on board? ()
A. Record of drafts
B. Hull reports
C. Anchor record
D. Machinery repair book
[单项选择]Forces within a drilling unit have caused a difference between the starboard and port drafts. This difference is().
A. list
B. heel
C. trim
D. flotation
[单项选择]A drilling bit which is doughnut shaped to permit recovery of the center portion of the hole drilled is called a().
A. diverter bit
B. hole reamer
C. core bit
D. conventional bit
[单项选择]emergency medicine是()。
A. 院前急救
B. 重症监护
C. 急诊科
D. 急诊医学
E. 急救护理学

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

截图扫码使用小程序[完全免费查看答案]
请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码