更多"[单选题]Project manager believes that "的相关试题:
[单选题]Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )
A.change the scope baseline
A.contact the customer to determine if the change adds value
B.call
C.meeting of the change control board
D.change the project's objectives
[单选题]In a project plan,when the project manager scheouies activities,he(or sha)often uses( )method,precedence relationships between acticities are represented by cireles connected by one or more arrows.The length of the arrow represents the duration of the relevant activity.
A.causality diagram
B.Gantt?chart
C.histogram
D.arrow djgram
[单选题]Risk management allows the project manager and the project team not to()
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
[单选题]The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).
A.periodic project reports,periodic visits to the customer,and telephonic exchanges
B.subordinates,project team members,and the project sponsor
C.one-time reports,weekly reports,and monthly reports
D.the telephone,facsimile,and data transmission
[单选题]He believes that from a military standpoint,the situation is under control.
A.position
B.point of view
C.knowledge
D.argument
[单选题]He believes that Europe must change or it will perish .
A.survive
B.last
C.die
D.move
[判断题]LCT 可以使用任何的Manager ID
A.正确
B.错误
[单选题]Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. ( ) is not a project selection method.
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
[单选题]Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element.
A.relationships
B.resources
C.stakeholders
D.deliverables
[单选题]Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).
A.fast tracking
A.what-if scenario analysis
B.resource leveling
C.critical chain metho
D.
[单选题]Project work packages are typically
decomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, and
monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting
[单选题]Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
[单选题]In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.
A.RBS
B.PBS
C.GBS
D.WBS