[单项选择]As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ______ .
A. performance reviews
B. variance analysis
C. trend analysis
D. earned value management
[单项选择]You are in the close project process. You are engaged in the activity to settle and close some contract agreements established for the project. Which of the following activities are you into
A. Administrative closure.
B. Contract closure.
C. Project executing.
D. Planning.
[单项选择]You are in the close project process.You are engaged in the activity to settle and close some contract agreements established for the project.Which of the following activities are you into ?()
A. Administrative closure
B. Contract closure
C. Project executing
D. Planning
[简答题]Working in a kindergarten you have to have
[单项选择]You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule,you should have spent ¥300,000 by this point. Based on these circumstances, your project could be best described as ______.
A. ahead of schedule
B. behind schedule
C. on schedule
D. having not enough information provided
[单项选择]At the beginning of project execution, you notice different opinions between team members relating to project work and deliverables and to the level of overall complexity. What should you do right now ?()
A. Give your team members some time to develop a common understanding of the project scope and product scope. Upcoming interface problems may be resolved later.
B. Use the risk management processes to identify and assess risks caused by misunderstandings and develop a plan with measures in order to respond to them.
C. Organize meetings to identify and resolve misunderstandings between team members in order to early avoid interface problems, disintegration and costly rework.
D. Use interviews in private with each individual team member to inform them of your expectations and your requirements in an atmosphere of confidence.
[单项选择]As a project manager,you advocate active participation of your team members-this is because you believe in ().
A. theory Y(McGregor model)
B. theory X(McGregor model)
C. Maslow's hierarchy of needs
D. referent power
[单项选择]As a project manager, you are aware that estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including risks. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution and product operations. The cost estimating process considers whether the expected savings can offset the cost of additional design work. Cost estimates are generally expressed in units of currency to facilitate comparisons both within and across projects. Cost estimates can also benefit from refinement during the course of the project to reflect on the additional detail available. For your project, which is in the initial phases, your team suggested a
A. -75% to+125%
B. -50% to+100%
C. -25% to+50%
D. None of the above
[单项选择]During half way to the project execution, you were assigned as a project manager. After careful reviewing of the project, you found that the project might take double the time that the previous manager estimated. However, the upper management has been told that the project is on schedule. The previous manager is an old friend of yours, what will you do ?()
A. Report your evaluation to the upper management
B. Have a team meeting to find the alternatives to meet the project schedule
C. Meet the previous project manager and turn the project back
D. Execute the project as planned by the previous manager
[单项选择]As a project manager,you try to use empathic listening skills to help understand another person's frame of reference, In following this approach,you should ().
A. mimic the content of the message
B. probe.then evaluate the content
C. evaluate the content,then advise
D. rephrase the content and reflect the feeling
[简答题]Object
Describe a project you did while you were studying
[单项选择]M: Hi. Melissa, how’s your project going Have you thought about going to graduate school Perhaps you can get into Harvard.
W: Everything is coming along really well. I have been thinking about graduate school. But I’ll talk to my tutor Dr. Garcia first and see what she thinks.
Q: What do we learn about the woman from the conversation( ).
A. She has been longing to attend Harvard University.
B. She’ll consider the man’s suggestion carefully.
C. She has finished her project with Dr.Garcia’s help.
D. She’ll consult Dr.Garcia about entering graduate school.
[简答题]part 2 & 3Describe a project you did while you were studying
Should children have homework Why
Do High-school students need to have a lot of homework
Do college students have part time jobs Why
How do we learn from our job
Why some parents choose to let their children study at home
Do you believe in Chinese education
What are the disadvantages of not having a computer
[简答题]part 2 & 3
Describe a project you did while you were studying
Should children have homework Why
Do High-school students need to have a lot of homework
Do college students have part time jobs Why
How do we learn from our job
Why some parents choose to let their children study at home
Do you believe in Chinese education
What are the disadvantages of not having a computer