[单项选择]When is integration performed
A. Project planning.
B. Project execution.
C. At key interface points.
D. At the end of each project management phase.
[单项选择]How is virtual reality surgery performed
A. It is performed by a computer-designed high precision device.
B. Surgeons wear virtual reality helmets to receive feedback provided by a computer.
C. Surgeons move robotic instruments by means of a computer linked to them.
D. A 3-D image records the movements of the surgeons during the operation.
[单项选择]
Many of the activities performed during the preliminary investigation are still being conducted in (1) , but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3) and the existing systems to enable an effective solution to be proposed and implementeD. Besides the (4) for process and data of current system, the deliverable from this phase also includes the (5) for the proposed system.
1()
A. analysis phase
B. design phase
C. implementation phase
D. maintenance phase
[简答题]Only after they had performed hundreds of experiments _____________________ (他们才成功地解决了这个问题)
[单项选择]Quality control should be performed ().
A. when the product of the project is completed to ensure that no defects exist
B. throughout the project life cycle
C. during the closeout phase but before final acceptance by the customer
D. as desired by the quality assurance department
[单项选择]The doctor in Singapore performed a valuable service by ______.
A. finding the subgroup of the virus
B. developing a cure
C. keeping his patients apart from others
D. reporting the outbreak to W. H. O.
[单项选择]Something unexpected has turned
A. up
B. back
C. out
D. around
[单项选择]During execution of a project which is performed for a customer on a T & M (time and material)contract base, a new project manager is taking over the assignment. He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. Which of the following should he do
A. Try to find some productive work for these staff members in the project and leave them on the team.
B. The best thing is to do nothing. The customer will not realize the problem anyway.
C. Try to find a responsible person for the over-assignment who can be made accountable.
D. Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.
[单项选择]All of the following must be performed during project initiating EXCEPT ().
A. identify and document business needs
B. create a project scope statement
C. divide large projects into phases
D. accumulate and evaluate historical information
[单项选择]The concerto was performed by a violinist of unquestioned ______ but limited imagination.
A. capacity
B. faculty
C. competence
D. aptitude
[多项选择]Which of the following services are performed by the forwarder on behalf of the consignee( )
A. Taking delivery of the goods from the carrier
B. Packing the goods for export
C. Arranging export customs clearance
D. Arranging import customs clearance