更多"If the design was wrong, the projec"的相关试题:
[单项选择]If that idea was wrong, the project is bound to fail, ______ good all the other ideas might be.
[单项选择]During execution of a project which is performed for a customer on a T & M (time and material)contract base, a new project manager is taking over the assignment. He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. Which of the following should he do
A. Try to find some productive work for these staff members in the project and leave them on the team.
B. The best thing is to do nothing. The customer will not realize the problem anyway.
C. Try to find a responsible person for the over-assignment who can be made accountable.
D. Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.
[单项选择]()is accepted as wrong is not necessarily wrong.
A. It
B. That
C. What
D. That it
[单项选择]The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the BEST choice for getting your project better organized
A. Adopt a life cycle approach to the project.
B. Develop lessons learned for each phase.
C. Develop specific work plans for each work package.
D. Develop a description of the product of the project.
[单项选择]While completing a project a project manager realizes be needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs ?()
A. Change to component A from component B. Component A costs more to purchase but has a lower life cycle cost than B
B. Change task A to be completed by resource B instead of Resource C, Resource B is a more experienced worker
C. Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources later
D. Remove a test from the project plan
[单项选择]Which sentence is wrong
A. She said, "What a lovely day it was!"
B. She said what a lovely day it was.
C. She said what was a lovely day.
D. She said it was a lovely day.
[单项选择]For a well planned project the project schedule is ______.
A. the agenda for carrying out the plan or a portion of it
B. not important, as each team member acts according to plan
C. used to generate a time table of major commitments for the project
D. both A and C
[单项选择]Being assigned as the project manager to a project you perform earned value Analysis and find the following results:EV=250000;PV=200000;AC=275000;BAC=500000.What is right ?()
A. EAC=400000
B. EAC=550000
C. BTC=400000
D. ETC=75000
[单项选择]Being the project manager in a software project which is currently initiated,you want to assess high level risks.What should you do ?()
A. Develop a preliminary scope statement and document initially identified risks in this document
B. Identify and analyze risk events using qualitative and quantitative techniques
C. Develop contingency plans and fallback plans in case the original plan proves Wrong
D. Discuss the risks documented in your risk register with the project key stakeholders
[单项选择]Educational development is bound up with economic progress.
A. in accordance with
B. consistent with
C. independent of
D. closely related to
[单项选择]A project manager has made a change to the project. What should he do next
A. Assign resource.
B. Revise the project plan.
C. Evaluate impact.
D. Request change control board involvement.
[单项选择]As a project manager,project plan development is an important element of managing projects.Which phase of the project management life-cycle does project plan development belong to ?()
A. Initiation process
B. Planning process
C. Execution process
D. Controlling process
[单项选择]The distinction between free morpheme and bound morpheme is whether morphemes can be other morphemes.
[单项选择]At the end of each project, the project team should prepare a lessons learned summary that focuses on all the following EXCEPT
A. sharing best practices with other project teams in the organization
B. warning others of potential problems
C. suggesting methods to mitigate risks effectively to ensure success
D. sharing only positive aspects of the project for future replication elsewhere in the organization
[单项选择]You are the project manager of a new project, which will construct a bridge on the River Nile in Egypt. Before initiating the project, you should ().
A. create a scope management plan to document:how the project scope will be defined, verified and controlled
B. develop a project management plan
C. determine specific activities that need to be performed to produce the various project deliverables
D. facilitate the formal authorization to start a new project