[单项选择]Risk management allows the project manager and the project team not to()
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses

更多"Risk management allows the project "的相关试题:

[单项选择]Risk management allows the project manager and the project team net to ( ).
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
[单项选择]You are a project manager for a small project.Your project was budgeted for ¥500,000 over a six-week period.As of today,you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000.According to your schedule,you should have spent ¥300,000 by this point.Based on these circumstances,your project could be best described as ().
A. ahead of schedule
B. behind schedule
C. on schedule
D. having not enough information provided
[单项选择]

Project manager believes that modifying the project scope may provide added value for the customer.the project manager should().


A. change the scopr baseline
B. contact the customer to determine if the change adds value
C. call a meeting of the change control board
D. change the project's objectives
[单项选择]A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should().
A. assign change tasks to project members
B. call a meeting of the configuration control board
C. change the scope baseline
D. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
[单项选择]A project manager can BEST resolve the differences between the requirements of one stakeholder and those of another by saying which of these statements
[单项选择]The work of Project Manager is chiefly concerned with
A. emergency relief programmes.
B. agricultural rehabilitation.
C. helicopter assisted surveys.
D. strategic planning,
[单项选择]During initiation, a project manager is planning the upcoming project execution team meetings. What should the project manager include in these meetings that would have the biggest impact on the project
A. Review of the action item lis
B. Review of identified risk
C. Assignment of tasks to team member
D. Estimating cost
[单项选择]You are the project manager managing the setting up of an oil rig in the Pacific Ocean. Which of the following could be a valid constraint when you are doing human resource planning for your project
A. Weak matrix organization structur
B. Unlimited budget since the project is very critical to meet compliance need
C. Oil price increasing above $60 per barre
D. None of the abov
[单项选择]The()provides the project manager with the authority to apply organizational resources to project activities.
A. project management plan
B. contract
C. project human resource plan
D. project charter
[单项选择]A project manager has to resolve two problems. However, both problems can occur in a single trial. In this situation, what is the BEST action the project manager can take
A. Develop a solution for each proble
B. Develop a solution that solves both problem
C. Use a statistically independent tria
D. N0 solution is needed, the two problems cancel each other ou
[单项选择]A project manager is following her company's internal project procedures to finish a project. These procedures call for the completion of lessons learned but do not describe who creates it. Who is involved in the creation of lessons learned
A. Project manage
B. Tea
C. Managemen
D. Stakeholder
[单项选择]The (73) provides the project manager with the authority to apply organizational resources to project activities.
A. project management plan
B. project charter
C. project human resource plan
D. project stakeholders
[单项选择]As a project manager, you are interested in the personal activities of team-members. Other than working with you on the project, the team members love to go out with you for lunch or an occasional game of golf. The power of the team members is ______ .
A. penalty
B. expert
C. legitimate
D. referent
[单项选择]The most successful project manager usually ______ .
[单项选择]As a project manager, you are in the process of creating a listing of all the project team members, their roles and communication information. This information should reside in the ______ (choose the best answer).
A. project plan
B. project team directory
C. performance reports
D. responsibility assignment matrix
[单项选择]The ______ provides the project manager with the authority to apply organizational resources to project activities。
A. project management plan
B. project charter
C. project human resource plan
D. project stakeholders
[单项选择]The most crucial time for project risk assessment is ()
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码