题目详情
当前位置:首页 > 职业培训考试
题目详情:
发布时间:2023-10-11 16:31:45

[单项选择]In your software development project you have planned for system testing from March 1st and the duration is 10 days.Two days before the completion of the system test,you can start the user acceptance test.The 2 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float

更多"In your software development projec"的相关试题:

[单项选择]In your software development project you have to wait for 5 days after ordering a new software and then only you can start integration testing.The 5 days in this case is an example of ().
A. lead
B. lag
C. delay
D. float
[单项选择]In your project,you have created performance reports to provide the status and progress information to different stakeholders.The results from the performance reports should be compared to the______.
A. project management plan
B. performance measurement baseline
C. earned value calculations
D. none of the above
[单项选择]In your project,you have identified list of identified risks,list of potential responses and root causes of risks.You should document this information in the______.
A. risk management plan
B. risk database
C. project plan
D. risk register
[单项选择]You will complete your project more easily if you take ______ of all the facilities here.
A. privilege
B. advantage
C. chance
D. care
[单项选择]Your plan about this project is excellent.
A. outstanding
B. wonderful
C. rare
D. so-so
[单项选择]In your project,you use the“develop project team”process to improve the competencies and interaction of team members to enhance project performance. The outputs from this process are ().
A. project staff assignments
B. team performance assessment
C. staffing management plan
D. project staff assignments,staffing management plan,team performance assessment
[单项选择]You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______.
A. all stakeholders in the performing organization
B. all project stakeholders
C. project team members and the project sponsor
D. people noted in the communications management plan
[单项选择]In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of ______ .
A. activity sequencing
B. activity duration estimating
C. schedule development
D. activity definition
[单项选择]In your project, you use product analysis to translating project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT ______ .
A. value engineering
B. value analysis
C. product breakdown
D. benefit/cost analysis
[单项选择]In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT ______ .
A. activities that are not required as part of project scope
B. activities that are to be performed as part of the project
C. activity identifier and scope of work description for each schedule activity
D. all the above are included in the activity list
[单项选择]In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A. PERT
B. CPM
C. parametric estimating
D. none of the above
[单项选择]In your project,you want to monitor and control project processes associated with initiating,planning,executing and closing.This will help you take corrective or preventive action to control project performance.In this context,what should you do first ?()
A. Review all project forecast
B. Detail all the activities of project team members involved in executing administrative closure for the projec
C. Review the project management plan and work performance information for your projec
D. Manage project risk
[单项选择]In your project, you are in the process of determining whether the activities being done as part of your project comply with organizational and project policies. This will be done as part of ______ .
A. inspection
B. quality audit
C. quality improvement
D. trend analysis
[单项选择]In your project,you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management.What could be a potential next step
A. Perform a structured review of project plans and assumptions,both at the total project and detailed scope level
B. Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar project
C. Conduct planning meetings to develop the risk management pla
D. Conduct interviews to quantify the probability and consequences of risks on project activitie
[单项选择]In your project,you can use all the following tools and techniques for risk response planning EXCEPT______.
A. strategies for negative risks or threats
B. contingent response planning
C. strategy for threat and opportunities
D. strategy for residual risks
[单项选择]In your project, you invest a lot of time in team development to increase the team's performance, which increases the likelihood of meeting project objectives. Which of the following indicators would you use to evaluate your team's effectiveness
A. Improvement in skills of team member
B. Improvement in competencies and sentiments that help the team perform better as a grou
C. Decrease in staff-attrition( fewer people leaving the project te
D. All the abov
[单项选择]As a project manager,project plan development is an important element of managing projects.Which phase of the project management life-cycle does project plan development belong to ?()
A. Initiation proces
B. Planning proces
C. Execution proces
D. Controlling proces
[单项选择]You look very well after your holiday; you have ______ weight.
A. put on
B. put up with
C. put away
D. put out
[单项选择]In which project phase do you have the GREATEST influence on project risk
A. Conceptua
B. Desig
C. Executio
D. Implementatio

我来回答:

购买搜题卡查看答案
[会员特权] 开通VIP, 查看 全部题目答案
[会员特权] 享免全部广告特权
推荐91天
¥36.8
¥80元
31天
¥20.8
¥40元
365天
¥88.8
¥188元
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《购买须知》
立即支付 系统将自动为您注册账号
请使用微信扫码支付

订单号:

截图扫码使用小程序[完全免费查看答案]
请不要关闭本页面,支付完成后请点击【支付完成】按钮
恭喜您,购买搜题卡成功
重要提示:请拍照或截图保存账号密码!
我要搜题网官网:https://www.woyaosouti.com
我已记住账号密码